OCT-NOV UPDATE














































G'day,
Our site supervisor was spot on about more work being done once the scaffolding was removed. Since my last blog entry, the following has been done;
* Plaster is up
* Skirts & Archs have been installed
* Staircase has been installed
* Doors are installed including entry door
* Tiles have been installed
* Kitchen & Joinery installed (although taken apart now due wrong order GrrrRR)
* Paint is about 75% complete
Cheers!!
Ken

Tuesday, September 22, 2009

September update



Brickwork 99% completed.... waiting on 2 window sills and we are done.
Roof tiles need to be put above garage & meals area and then we are officially locked up.
Scaffolding has been taken down, looks much more neat and less cluttered. Now I can thoroughly inspect the brickwork.
Apparently it's full steam ahead now that the scaffolding has been removed.....

Friday, September 4, 2009

September




Brick work still not finished, awaiting on garage beam to go up before brickwork is completed.

Wednesday, August 19, 2009

Friday, July 3, 2009

Frames



Base Stage








Must say we are delighted with the progress so far, been approx 1 month since they have started. We are now at the frame stage, just awaiting roof trusses and 1st floor windows to be installed. Hopefully this can be achieved by the end of next week.

PS: Apologies, slab photos are poor quality thanks to my little girl who destroyed my good camera phone, had to use an old phone to take these pics.

Tuesday, June 9, 2009

Site scrape


Started the site scrape today in very muddy conditions, shouldn't complain, we need the rain!