Sunday, November 22, 2009

OCT-NOV UPDATE














































G'day,
Our site supervisor was spot on about more work being done once the scaffolding was removed. Since my last blog entry, the following has been done;
* Plaster is up
* Skirts & Archs have been installed
* Staircase has been installed
* Doors are installed including entry door
* Tiles have been installed
* Kitchen & Joinery installed (although taken apart now due wrong order GrrrRR)
* Paint is about 75% complete
Cheers!!